Discussion with the Harbor Committee regarding implementation of the recent Harbor Master Plan Study. The discussion will focus on tasks and a timeline. (Public comment is welcomed and encouraged.)
ACTION: No Council action anticipated.
Summary:
Staff representatives and the Harbor Committee will present a brief overview of the Harbor Master Plan and proposed timeline for implementation. A copy of a concept timeline is attached. Click here to find a copy of the complete presentation. Click here to view a copy of the Habor Master Plan Report.