Board of Selectmen Minutes 06/19/2012
                       Town of North Stonington

                            Board of Selectmen    

               New Town Hall Conference Room

                                June 19, 2012

  -                               7:00 PM

 

MINUTES

Call to Order -7:03 PM with Selectmen Mullane, Donahue, and Selectman Murphy arrived at 7:15 PM.

Public Comments and Questions-Request to revise Old Business Item #4 title

Minutes-A motion was made by Selectman Donahue and seconded by Selectman Mullane to approve the minutes of June 12, 2012, carrying.  2-0

A motion was made by Selectman Donahue and seconded by Selectman Mullane to approve the minutes of June 14, 2012, carrying.  2-0

Correspondence

Old Business-

1.           Tribal Issues-Acknowledgement Issues

Executive Session-A motion to enter Executive Session at 8:33 PM to update Selectmen on latest events in the Eastern Pequot/Paucatuck Eastern Pequot group litigation. Came out of session  at 9:07 PM No action taken

  2.   Subdivision Review and Planning and Zoning Issues

              Affordable Housing/Incentive Housing regulations                        No reports

              Milltown Commons

  3.   Permanent School Building Project Committee

              A. Permanent School Planning and Building Committee Project-No report

  4.  YMCA Property-A meeting is being arranged with the Attorney General’s office to discuss the town’s request.

  5.         Kingswood/Meadow Wood drainage staff working with town’s attorney to support arbitration.

  6.  Hewitt property

              A.  Committee Report-Status report on leases next meeting

              B.  Dam Repairs-Re-Engineering—No new information

  7.  Boombridge Road Bridge- Design-Additional work required on Hydraulics for ConnDOT, awaiting approval.  This has caused a delay in design progress.

  8.  Grant applications/administration

              Water Study Ex. 92 X I95-Consultant is working on RFP

              Rec Area Basketball, Tennis Courts-Almost 100% complete

  9.  Board and Commission appointment

              Permanent School Planning and Building Committee                                   No action

              Water Pollution Control Authority

              Cable TV Advisory Committee

              Economic Development Commission

10.  Flood Damage Status Report/Repairs Update/ Action Items

              Main Street Bridges-Contractor working on hardware side abutments, also working on damaged neighbors stone retaining wall

              Village Green Bridge-Received Inland Wetlands approval on bridge repair design

11.   Budget 2011-12 Year End Transfers and Additional Appropriations-Board of Finance approved all items requested last week.

12.   Budget 2012-13/Setting of Mill Rate-  Both General Government and Board of Education budgets failed at first referendum vote.  BOF/Selectmen has made additional cuts and BOF has set the mill rate at 25.25 for FY 2012-12.

New Business-

1.           Tax Refund(s)-None presented

2.          

Public Comments and Questions