  • Call to Order:  Chairman Dan Spring called the meeting to order at 6:04 PM.  Mike Urgo, Emile Pavolvics and Brent Woodward were present. Peter Nimirowski arrived at 7:34.   Mustapha Ratib was absent.
  • Public Comments and Questions:~ Joe Gross provided the Board a template he had created to track additional appropriations and transfers as they occur.
  • BOE 2013-2014, Budget Proposal:  Mr. Peter Nero, Superintendent of Schools, made opening remarks noting that the proposed FY 2013-2014 budget represented a departure from the last six budget years in that the recommended increase of 5.33 percent was 4.6 percent greater than the average of those six years.  The 5.33 percent increase ($644,387) translates into a recommended education budget of $12,739,669.  The following presenters provided detailed explanations of budget breakdowns for their respective areas of responsibility.
  • Mrs. Veronica O. Wilkison, Elementary School Principal
  • Mr. Christopher Sandford, High School/Middle School Principal
  • Ms. Susan E. Costa, Special Education Director
A summary of area budgets is shown in the following table.

  

Area
Approved           FY 2012-13
Proposed
FY2013-14
Increase
Elementary
$2,337,345
$2,498,403
$161,058
High/Middle
$4,449,921
$4,520,599
$70,678
Special Ed
$2,154,603
$2,361,946
$207,343
IT
$78,240
$135,706
$57,466
Operations
$3,075,173
$3,3,223,075
$148,842
Area
Approved           FY 2011-12
Proposed
FY2012-13
Increase
Total Budget Increase
$12,095,282
$12,739,669
$644,387



Significant cost drivers, including percent increase above the previous year, are shown below.

  • Special Education Related Services                              128.57%
  • Instructional Supplies                                          12.50%
  • Other Expenses, Schools                                 21.49%
  • Nursing Supplies                                                14.29%
  • Replacement of Equipment                                        202.14%
  • Employee Insurance                                              10.01%
  • New Equipment                                           47.41%
  • Tuition                                                         11.65%
  • BOS: Budget Prep; Proposed Capital Projects; OTH Bridge Close; CNR Review:  Proposed capital projects and estimated costs are shown below in the table.
Description of Work
Estimated Cost
Town Hall Parking Lot River Wall Repair
$350,000
Village Green Bridge Repair
$150,000
Hewitt Dam Repair
$350,000
New Firehouse Complex
$3.64M

        
        The Old Town Hall bridge closeout reported a $152,000 under budget cost savings.  The actual savings to the Town is 25% or $38,000 as FEMA would have paid the balance.

        The CNR review was deferred.

5.      Strategies: Budget Format:  Due to the absence of Mustapha Ratib, who is leading the effort, no specifics were discussed.  The Board is confident that proposed changes will not impact the budget process schedule.  

6.      Previous Minutes:   Mike Urgo moved to approve the minutes of March 27, 2013 as presented.  The motion was seconded by Peter Nimirowski and passed 5-0-0.  
  



7.      Adjournment:  A motion was made by Dan Spring to adjourn.  The motion was seconded by Peter Nimirowski and passed 5-0-0.  The meeting was adjourned at 9:34 PM.

Respectfully Submitted,
482013_113413_0.png
Brent Woodward
Secretary, Board of Finance