CONSERVATION COMMISSION AGENDA 8/29/12 @ 12:30 PM
Site Visits took place on August 28 @ 12:30 PM.
- CONTINUED HEARING NOI SE 12 – 659 GEORGE SOURATI FOR 12:30 PM
GRIN ACRES FAMILY LIMITED PARTNERSHIP; 15 Nickerson Farm Lane; AP 21 – 10, 12, 13. Eligible Voters: Pam, Sandy, Donald, Wesley: This is a response to the Enforcement Order issued on 12/28/11 for clearing near a perennial stream, in a wetland and buffer zone.
The application seeks to restore previously disturbed wetland and buffer zone resource areas and remove and replace an existing asphalt driveway with a concrete surface and a water runoff drainage trench with crushed stone. The driveway and trench are approximately ten feet from a wetland edge at the closest point.
2. NOI SE 12- 664; CHRIS ALLEY FOR PETER & SUSAN BERNARD 12:40 PM
5 Shotnaigher Lane; Map 34 Lot 1.1: Renovate an existing single-family dwelling, add a bathroom and reconfigure the driveway and parking area with associated site work. The work is within the 100-foot buffer zones of several Bordering Vegetated Wetlands. The closest activity is 25 feet from a wetland edge.
3. NOI SE 12 - 665; CHRIS ALLEY FOR LAUREN WALTERS; 12:45 PM
18 Greenhouse Lane; Map 33 Lot 32: Stabilize the Atlantic Ocean Coastal Bank by: 1. Brush cutting along the top of the bank for equipment access. 2. Install 3 courses of coir logs. A walk-behind bobcat will be used to prepare the lower course. A white sand fill will be used to build up the grades for beach grass planting.
4. NOI SE 12 – 662 GEORGE SOURATI FOR ROBERT LABAREE; 12:50 PM
Menemsha Inn Rd.; AP 21 – 38.2. Build and maintain a beach stairway down the Vineyard Sound Coastal Bank for year-round use. A four-foot wide walking path from the planned site for a new single-family residence to the stairway is also proposed. The walkway is in the 100-foot buffer zone of the coastal bank. A driveway, water well with trenching and buried utility lines for the proposed new house are also planned. This activity is within a 100-foot buffer zone of a Bordering Vegetated Wetland and in the second 100-foot section of the Riverfront Zone.
5. FOLLOW UP SE 12 – 661; JOHN ABRAMS FOR BLUE SKY MV, LTD (BLUE HERON FARM); AP 11-23.3: Review revise pool site plan and landscape plan as required in the Order of Conditions.
6. ADMINISTRATION:
Minutes 8/1/12.
Signatures:
Order of Conditions Grin Acres; SE 12 – 659; AP 21-10, 12, 13 (if voted).
Order of Conditions Bernard; SE 12 – 664; AP 34-1.1 (if voted).
Order of Conditions Walters; SE 12 – 665; AP 33-32 (if voted).
Order of Conditions Labaree; SE 12 – 662; AP 21-38.2 (if voted).
- NEXT MEETING: Wed., Sept. 5 @ 12:30 PM. Site Visits will take place on Sept. 4. Chuck H. needs to be away again.
|